Skip to main content

Free Shipping on orders over $500

Quick Answer

How do you document a pile driving log?

Record blow counts for every foot (or 0.25m) of pile penetration, starting from initial hammer contact. Log the pile ID, location, pile type and length, hammer model, hammer energy setting, and driving criteria (required blow count or set per blow). Record total pile penetration depth, final tip elevation, cutoff elevation, and whether the pile reached refusal or met the specified driving criteria. Submit the completed logs to the geotechnical engineer of record for review and acceptance before the next phase of foundation work.

How to Document a Pile Driving Log for Foundation Work

Applies to: driven steel H-piles, pipe piles, precast concrete piles, timber piles, helical piles with torque logging

Pile driving logs are permanent legal and structural records. They document the load-carrying capacity evidence for each foundation pile — the blow counts that the geotechnical engineer uses to evaluate whether the pile achieves design capacity. Incomplete or inaccurate pile logs can lead to rejected piles, additional load testing, and in worst cases, foundation remediation after the structure is built. Knowing how to keep a proper pile driving log is a critical field skill for any crew running a pile rig.

Step 1: Set Up the Log Header Before Driving Begins

Complete the pile log header before the hammer touches the pile. Required header fields:

Project name and address. Pile ID (from the pile plan drawing — each pile has a unique designation such as P-1, P-2, or a grid reference). Pile type (HP14x89, 16-inch open pipe pile, 14-inch square precast, etc.). Pile specified length and actual delivered length. Hammer identification: make, model, and serial number. Hammer rated energy (in foot-pounds or kJ). Cushion type and condition (for precast piles). Driving criteria: the blow count or set-per-blow value the geotechnical engineer requires for acceptance. Date, time driving began, and inspector name. Weather and site conditions at time of driving.

A log that is missing the hammer energy setting or driving criteria cannot be reviewed by the geotechnical engineer — they need to know what hammer was used to interpret blow counts in terms of soil resistance. If you do not have the hammer specifications, get them from the pile subcontractor before driving begins, not after.

Step 2: Record Blow Counts by Foot of Penetration

Record the number of hammer blows required to advance the pile each foot (or each 0.25m for metric projects). Starting from the ground surface (or from the point of initial hammer contact if the pile is pre-augered), count blows from 0 to 1 foot, 1 to 2 feet, 2 to 3 feet, and so on until the pile reaches final tip elevation.

Mark the pile in one-foot increments before driving — use paint, chalk, or tape. If the pile is not marked, it is impossible to accurately record blow counts per foot of penetration while the rig is running. The pile crew foreman should mark the pile before the rig positions over the pile hole.

Note any unusual events during driving at the depth where they occur: sudden increases in penetration rate (possible weak layer, void, or pile tip damage), sudden increases in blow count (cobbles, hard strata, obstructions), pile run (pile advancing under its own weight without hammer blows), or pile refusal (defined below). These observations are as important as the blow counts themselves for geotechnical interpretation.

Step 3: Record Driving Criteria and Final Set

Most driven pile acceptance criteria are specified as a required minimum blow count over the last foot of driving, or a set per blow (penetration per blow in the last 10 blows). Common criteria examples: "minimum 20 blows per foot over the last foot" or "set not to exceed 0.25 inches per blow in the last 10 blows."

When the pile approaches the anticipated final penetration depth, alert the inspector to watch closely. Record the blow count and set measurement at the last foot in detail. For set-per-blow criteria, measure the total penetration over the last 10 blows and divide by 10. Use a steel rule or tape held against the pile while driving to measure penetration per blow accurately.

Refusal is defined differently by project specifications — commonly when the pile fails to advance more than 0.25 inches per blow for 10 consecutive blows, or when blow counts exceed 100 blows per foot. Record the depth at which refusal occurs. Refusal before design tip elevation requires notification of the geotechnical engineer before continuing.

Step 4: Record Final Pile Dimensions and Elevations

After driving is complete, record: total driven length (from ground surface to pile tip), tip elevation (calculate from the known ground elevation at the pile location minus the driven depth), cutoff elevation (the elevation at which the pile will be cut to match the cap design), and stick-up length (distance the pile projects above the cutoff elevation).

Survey the pile cutoff elevation with a level or total station against the project benchmark. Do not calculate it solely from tape measurements — elevation errors from a misread tape propagate into the pile cap elevations and can result in rebar couplers at the wrong height. Record the surveyed cutoff elevation on the pile log.

Step 5: Submit Logs to the Geotechnical Engineer for Acceptance

Completed pile driving logs must be submitted to the geotechnical engineer of record for review and acceptance before the pile caps are poured. The geotechnical engineer will review blow counts against the soil boring logs and the design driving criteria to confirm each pile achieves adequate capacity.

Logs should be signed by the field inspector or the pile inspector of record. Many jurisdictions require a special inspector for all driven pile work — confirm inspection requirements before driving begins. Unsigned or incomplete logs are typically rejected and require reconstruction from field notes, which is difficult after the fact.

Gradelog field records can capture pile driving data in real time — blow counts by depth, hammer ID, criteria, and GPS location of each pile — producing formatted pile logs automatically at the end of each driving day.

Frequently Asked Questions

What is pile refusal and what do I do when it happens?

Pile refusal occurs when a pile cannot be advanced further by the hammer, typically defined as less than 0.25 inches of penetration per blow for 10 consecutive blows. When a pile hits refusal before reaching design tip elevation, stop driving and notify the geotechnical engineer of record immediately. Options include: accepting the pile at the refusal depth if bearing capacity is demonstrated, using a larger hammer, pre-augering through the obstructing layer, or relocating the pile. Do not continue hammering past refusal without geotechnical guidance — over-driving causes pile damage.

What information is required in a pile driving log?

Required fields include: pile ID and location, pile type and length, hammer make and model with rated energy, cushion type, driving criteria, blow counts by foot of penetration, events noted during driving (runs, refusals, obstructions), final tip elevation, cutoff elevation, date, inspector name, and geotechnical engineer of record. The exact requirements vary by project specification and jurisdiction — review the project's special inspection plan before driving begins.

Can I use an app to record pile driving logs?

Yes. Digital field recording tools like Gradelog allow real-time pile log entry with GPS location tagging, automatic blow count tabulation, and formatted PDF output for geotechnical submission. Digital logs reduce transcription errors from field notes to office documents and create a timestamped, uneditable record. Confirm with the project geotechnical engineer and special inspector that digital log format meets project submission requirements.

What happens if blow count records are missing for some depths?

Missing blow count records for any depth interval require an explanation. If a pile section was pre-augered, note the augered depth range and restart blow count logging at the bottom of the pre-augered hole. If records were lost due to a field error, document what happened and what is known. Geotechnical engineers will flag piles with missing blow count records — incomplete logs rarely pass without a technical explanation from the pile inspector.

Capture pile driving logs in real time in the field with Gradelog. Blow counts by depth, hammer data, GPS pile location, and automatic formatted log output for geotechnical submission. Free to start at gradelog.com.

Do it right the first time

Skip the guesswork — let the Gradelog AI walk you through it on site

Gradelog is the field AI trained on procedures exactly like this one. Instead of reading steps, ask it anything about your instrument, your grade, or your spec — and it guides you through setup, calibration, and shot-by-shot work in real time, then turns it into an inspector-ready as-built report.

  • In-depth AI answers for your exact instrument
  • Guided setup, calibration & grade checks
  • Auto as-built reports inspectors accept
  • Works with every laser, level & rover
Start 14 Days Free
14 days free on any plan with code EXPRESSTOOLS14
Card required · cancel anytime before day 15 · then your selected plan
Gradelog — Earthwork Operating System

Free 30 days with every Express Tools purchase

Your equipment. Your data. All in one place.

Gradelog is the field-execution platform built for grading and earthwork crews. Log grade shots, track cut/fill, document phases with photos, and generate as-built reports — from the cab to the office.

  • Grade shots & cut/fill tracking per job
  • Photo documentation by phase, task, and equipment
  • As-built reports ready for inspector sign-off
  • AI field assistant — troubleshoot on the jobsite
Gradelog dashboard — live field overview with grade shots, photos, and equipment status

Built by the same team as Express Tools

Try Free →

30 days

Free trial

8 languages

Supported

iPhone + Android

Works on